More on the work that remains to be done on the CBS tower from an STA extension request by WNEU, which was approved today:
WNEU’s new repack channel antenna was temporarily installed at a lower height to
allow WNEU to cease operations on its pre-auction channel by the phase 4 deadline, and because
WNEU’s new repack channel antenna cannot be moved up to its final position until American
Tower completes additional work needed on top of the tower. The additional tower work needed
includes the removal of an existing double-stacked broadband antenna system shared by four
repacked television stations and two FM radio station antennas, the installation of a new antenna
support structure for the new top-mounted broadband antenna to be shared by the four repacked
television stations, and the reinstallation of the FM antennas, among other things. This work is
currently estimated to be completed in Spring 2020. Accordingly, an extension of the WNEU
STA is hereby requested so that WNEU may continue serving its viewers with its interim
facilities.
https://enterpriseefiling.fcc.gov/dataentry/api/download/attachment/25076ff36efa9535016efb2244ca0341
WNEU today requested an extension of this just-approved request until July 27, 2020, adding a few more details, including that the two FM stations which must have their antennas temporarily removed are WBUR and WKLB. WBUR requested that work not begin until the end of December, since they are currently running an on-air fund raising event:
https://enterpriseefiling.fcc.gov/dataentry/api/download/attachment/25076f916eff50b9016f0fbf01601b36