WFLF finally switched back to their main transmitter site at full power (100kw) tonight at 620 pm (12/2). We had to move to a temporary transmitter site while major structural work was done on the 1000 ft tower North of Port St Joe. Weather (including numerous days with high winds at 1000 ft), fabrication problems and other factors extended this project by over 30 days......Crown Castle owns the tower and was responsible for the work. We had been on the temporary transmitter site (300 ft tower with 6kw ERP) since late September........and they got all the strobies working on the tower too Tibbs!